WEST PORT PIER EXTENSION AND EXPANSION PROJECT

Projemiz Hakkında

EMPLOYER Batı Anadolu Çimento Sanayii A.Ş.

DATE OF REALIZATION
2015-2016

41,00m90,00m = 3.690,00m² pier extension, 18,00m192,00m = 3.456,00m² extension. A total of 7.146,00m² of pier extension and lengthening construction was carried out. (In this Project, 322,00 pieces (7.333,00Ton steel pipe) 1.016,00mm/16,00mm, 13.500,00m³ Ready-mixed concrete, 2.030,00 tons of Rebar, A120 rail 540,00m, 32,00 pieces of 150 ton Scaffolding father, 18,00 pieces of 25,00 ton Anele, 17.491,00m² Water repellent material was applied under the scaffolding, 8.000,00m² coating concrete was made on the scaffolding, 267,00 tons of various iron production was made).